Shell C-Store & Carwash – Lewis Farm
9805 & 9809 Winterburn Road NW
Edmonton, AB
Start Date: April 30, 2020
Substantially Complete: October 23, 2020
C-Store: 171m2
Construction Requirements:
- Continuous flight piles (CFP) used for building foundation due to soil conditions
- Structural slab used for C-Store slabs
- Structural steel frame with steel stud infill used for the C-Store
- Exterior finishes: Combination of masonry and metal cladding exsulation wall system
- SBS roofing system used for the C-Store roof
Carwash: 129m2
Construction Requirements:
- Continuous flight piles (CFP) used for building foundations due to soil conditions
- Structural slab construction used for carwash interior slabs & entrance/exit ramps
- Concrete masonry wall structure c/w 8” hollow core roof panels used for the carwash
- Exterior finishes: Combination of masonry and metal cladding exsulation wall system
- SBS roofing system used for the carwash roof
Canopy: 246m2
- 3 pump, 6 lane retail fuel service consisting of:
- 1 – 100,000 liter underground storage tank:
- 100,000 litres regular grade fuel
- 1 – 100,000 liter compartmentalized tank:
- 50,000 liters premium grade
- 50,000 liters diesel fuel